Altum Precision

Service: Rental factory / Rental factory contractor / Factory contractor
(Wholly owned by Engtek group – Malaysia) The project of Altum is slightly different but by all means more challenging. We were given 30 days to finish renovation work for the new factory rented from TICON and another 3 days to transfer production line from existing plant to the new one. The schedule is already tight, however like other renovation work. More pressure come from the transferring part as we had to ensure no interruption of existing operation under no circumstance during transferring period. Working under the instruction of Mr.Chua, Assistant General Manager of Altum, we successfully perform the project in a timely and again satisfactory manner.